Properly designed discrimination and back-up protection minimises the disruption and cost of guarding against electrical faults. Janet Roadway, product manager for power circuit breakers in the UK with ABB, argues that only those designers with real training and experience can achieve the right balance.

Balancing act: damage vs. disruption

Protecting people and property is paramount in the event of a short circuit or overload. It’s vital that a fault in the microwave of a hospital kitchen triggers a circuit breaker to cut the supply to the faulty oven to prevent a fire, for example. On the other hand, no one wants to disrupt the entire hospital with an electrical blackout each time a light bulb blows.

Striking a balance between maintaining maximum protection for the minimum disruption is far from straightforward and best left to specialists. It has been observed that some electrical consultants are now attempting to pass this responsibility on to panel manufacturers or site contractors, who often lack the training and experience to tackle the job.

As a leading manufacturer of circuit breakers, ABB is increasingly being approached to carry out discrimination studies. Naturally, any responsible manufacturer will be able to provide discrimination tables and other relevant data on their equipment. However, factoring in protection against electrical faults is really a strategic job that should be carried out by whoever is designing the electrical system as a whole.

The first step in the process is a fault protection study, which asks, "what will happen if things go wrong?" Its first priority is to ensure full protection for people and property. Its secondary aim is to minimise disruption and provide continuity of service.

A system for distributing electricity throughout an office block or hospital typically has an inverted tree structure. At the top is the main switchboard, fed by a HV/LV transformer and protected by a large air circuit breaker (ACB). This feeds several out-going moulded-case circuit breakers (MCCBs).

Each of these then feeds a number of smaller distribution panels, which may be protected by more MCCBs, miniature circuit breakers (MCBs), or fuses, depending on the current they have to deal with in normal operation and the fault currents they may encounter. Eventually the electricity reaches the equipment that provides the load on the system, such as the microwave in our example.

Selective action through discrimination

Discrimination aims to ensure that only the protection device immediately upstream of a fault will trip, leaving the rest of the supply intact. If all the protection devices in a supply chain are set to blow instantly at the same threshold current, they may all trip at once if there is a short circuit. By equipping different points in the supply chain with protection devices that have adjustable tripping characteristics, the designer can provide the discrimination needed to minimise the disruption caused by a fault.

There are three basic approaches to discrimination. The first is to use devices set to trip at higher threshold currents further up the supply chain. The second is to place a time delay on circuit breakers at a higher level in the chain. By the time a fault current would cause them to trip, a circuit breaker lower down the chain should already have isolated the fault and things should be back to normal. The third approach is to discriminate on the basis of the total energy passing through the circuit breaker. This is related to the square of the current and time. This third approach is the best way to achieve a system that is optimised for both current rating and physical dimensions.

It all sounds fairly straightforward, but the relationship between different devices is complicated by the potential for interaction between them.

Interactive protection

As well as the designed-in tripping mechanism that responds to the size and duration of the fault current, a high fault current can generate magnetic repulsion between the contacts inside a circuit breaker. This effectively loosens the contact between the surfaces, increasing impedance and reducing the current flowing through the device. This in turn will limit the current flowing to the next device in the supply chain.

This is not something that will show up on the charts of time vs current that are used to define and predict the way each protection device behaves.

Very fast acting devices may also limit the current. This is because they act before the current has time to reach its peak.

Manufacturers therefore provide discrimination tables to give reliable predictions of how a particular combination of devices will behave in practice. These show that the level of discrimination actually available is often higher than the isolated behaviour of individual devices suggests.

In the end, however, total discrimination may not be feasible. The level of fault current that would need to flow or the time for which it would be allowed to run may simply cause too much stress and long-term damage to the distribution system. Achieving a balance between the potential damage and the disruption caused by a fault is ultimately a judgement call that is best made by experienced electrical consultants.

Optimising cost and protection

The other balancing act that the electrical consultant on any large project must try to pull off is maximising the level of fault protection while minimising the cost and space devoted to protection devices. It’s not just about initial equipment costs: Office buildings charge by the square metre, for example, so an oversized switch room will cost the owner a lot of money over the life of a building.

The regulations governing low-voltage distribution enable designers to get round this using back-up protection. Back-up protection exploits the current-limiting effect of upstream circuit breakers to enable the installation of downstream devices that have a smaller rated breaking capacity than they apparently need. This is because the fault current the downstream breaker "sees" is restrained by the upstream device. Instead, only the upstream device needs to have a breaking capacity to match the highest possible fault current.

It’s obviously vital to get back-up protection right. If a circuit breaker experiences a higher fault current than it’s rated for, it could be damaged or even explode.

The mechanisms behind backup protection are extremely complex. Added to this is the fact that data is almost always unavailable to the end-user, having been obtained from experiments carried out in specialist power laboratories. This effectively ties the designer to a single manufacturer who can guarantee that back-up protection matches the level required.

The other drawback of back-up protection is that it effectively rules out the possibility of total discrimination. There is a threshold fault current called the takeover current, above which both the circuit breakers will trip. Total discrimination is only possible for fault currents below this level.

Even this brief discussion shows that there is more to designing an optimal fault protection system than just looking at the characteristics of individual protection products. Only by appreciating the potential for interaction between devices can a designer balance all the conflicting needs of safety, continuity of supply, space and cost.

It takes an experienced practitioner to juggle all these requirements and come up with the optimum solution for electrical fault protection. So it’s always worth calling in specialist help, rather than relying on a general site contractor. The right designer will protect the installation from damage, minimise disruption and save the client money in the long run.

A simple presentation explaining about discrimination can be downloaded by clicking on the 'Downloadable attachments link' below this article.

How can ABB help?

ABB’s new DOCwin 2.1 software package for the design and dimensioning of electrical installations is available now, free of charge to designers and consultants.

The DOC (Design Optimisation on Computer) win 2.1 software has been developed by ABB to cover virtually anything that an electrical installation designer could demand of a calculation package from calculating an entire installation or just solving a simple local problem.

DOCwin 2.1 is compatible for use with Windows 9.x, Me, NT 4.0 or 2000. Registered users are able to take advantage of a web or telephone help desk together with a web-based upgrade service that enables them to benefit from ABB’s ongoing development of the software tool.